Dubai airport expansion moved forward with AED56.5 billion, or about $15.4 billion, in new construction contracts. The packages cover passenger facilities, transport links and essential power systems at Al Maktoum International Airport.
Crown Prince of Dubai Sheikh Hamdan bin Mohammed bin Rashid Al Maktoum announced the awards. The contracts will allow work to proceed at the same time across several parts of the project’s first phase.
Some packages cover underground works for the West Terminal Building and Concourses 1 and 4. These include basements, tunnels, access ramps, short-term parking and a Ground Transportation Centre.
The work also includes metro connections, bridges and routes for ground service equipment. In addition, crews will install supporting networks for electricity, water, telecommunications, sewage and stormwater drainage.
Meanwhile, contracts for Concourses 2 and 3 focus on above-ground construction. They cover structural frameworks, rotundas, steel bridges and supports for passenger boarding bridges.
Workers will also install large-span steel roofs, façades and roofing systems. The packages include interior finishes, mechanical and electrical systems, plumbing and specialized airport equipment.
A separate power contract covers two main substations rated at 132/11 kilovolts. Contractors will build, test and commission the substations, cabling and related infrastructure to serve airport buildings and operational systems.
The new awards follow an earlier round worth approximately AED23.815 billion. Those contracts covered enabling and underground work, along with an automated people mover and baggage-handling systems.
Together, awarded packages now total about AED80 billion. Dubai Aviation Engineering Projects oversees planning, procurement, construction sequencing and coordination among government bodies and delivery partners.
The project aims to prepare Dubai for long-term growth in passenger and cargo traffic. Sheikh Hamdan said the airport also supports the Dubai Economic Agenda, known as D33, which seeks to double the emirate’s economy and strengthen global connections.
Construction teams are already working across terminals, concourses, tunnels, transport areas and utility zones. Enabling work near Concourses 2 and 3 and the airport’s central area is nearing completion.
Across the wider site, excavation has exceeded 24.23 million cubic metres. Crews have also completed more than 5.2 million cubic metres of backfilling and installed 7,635 piles.
Work on the substructures of Concourses 2 and 3 has placed over 875,603 cubic metres of concrete. Teams have also installed more than 226,270 tonnes of reinforcing steel, preparing those areas for above-ground construction.
The combined workforce across the contract packages numbers about 14,000 people. Cumulative working hours have surpassed 21.3 million as construction progresses across multiple sites.
Sheikh Ahmed bin Saeed Al Maktoum said the project had entered a large-scale construction phase. He added that teams would advance work in parallel while maintaining quality and safety standards.
Once operational, the airport is expected to provide capacity for growing airline, passenger and cargo demand. Dubai airport expansion now includes extensive terminal foundations, concourse structures, transport connections and utility systems.